Backlog − Directional
Change in ownership scenarios and lease contract duration have the potential to significantly impact the Company’s future cash flows, net debt balance as well as the profit and loss statement. The Company therefore provides a pro-forma Directional backlog based on the best available information regarding ownership scenarios and lease contract duration for the various projects.
The pro-forma Directional backlog at the end of 2021 reflects the following key assumptions:
- The Liza Destiny (FPSO) contract covers the basic contractual term of 10 years of lease and operate.
- The Liza Unity (FPSO) contract covers a maximum period of two years of lease and operate within which the unit will be purchased by the client. The impact of the sale of Liza Unity (FPSO) is reflected in the Turnkey backlog at the end of the maximum two year period.
- The Prosperity (FPSO) contract awarded to the Company in October 2020 covers a maximum period of lease and operate of two years, within which the FPSO ownership and operation will transfer to the client. The impact of the subsequent sale of Prosperity (FPSO) is reflected in the Turnkey backlog at the end of the maximum two year period. Normally, the Company would not yet take the operating and maintenance scope of this contract into account although it has been agreed in principle, pending a final work order. However, to be consistent with the prior year and to better reflect the current reality, the pro-forma backlog set out below takes the operating and maintenance scope on Prosperity (FPSO) into account.
- With respect to FPSO for the Yellowtail development project, for which the full lease and operate contract award is subject to necessary government approvals and final work order to be received from the client, the amount included in the pro-forma backlog is limited to the value of the initial limited release of funds to the Company to begin FEED activities and secure a Fast4Ward® hull.
- On December 20, 2021, the Company signed an agreement with China Merchants Financial Leasing (Hong Kong) Holding Co., Limited (CMFL) regarding the future divestment of 13.5% equity ownership in the Sepetiba special purpose companies. This transaction has not yet been reflected in the backlog as it remains subject to various approvals, which include the consent from co-owners, lenders and export credit agencies.
- The FPSO Almirante Tamandaré partial divestment to partners (45%) was concluded after the reporting period on January 25, 2022. As a consequence, the ownership share (55%) in the 26.25 years lease and operate contracts was added to the Lease and Operate backlog and the partial divestment to partners (45%) was added to the Turnkey backlog
- The pro-forma backlog of FPSO Alexandre de Gusmão takes into account the initially targeted Company ownership share (55%) in the 22.5 years lease and operate contracts. As a consequence, this targeted share was added to the the Lease and Operate backlog whereas the partial divestment to partners (45%), which remains subject to finalization of the shareholder agreement and various approvals, was added to the Turnkey backlog.
The pro-forma Directional backlog at the end of December 2021 increased by almost US$7.9 billion to a total of US$29.5 billion. This increase was mainly the result of (i) the awarded contracts for the FPSO Almirante Tamandaré project and the FPSO Alexandre de Gusmão project and (ii) the awarded initial scope to begin FEED activities and secure a Fast4Ward® hull for the FPSO for the Yellowtail development project less turnover for the period consumed of US$2.2 billion.
in billions of US$ |
Turnkey |
Lease & Operate |
Total |
---|---|---|---|
2022 |
1.5 |
1.6 |
3.1 |
2023 |
0.8 |
1.6 |
2.4 |
2024 |
1.5 |
1.8 |
3.3 |
Beyond 2024 |
1.2 |
19.5 |
20.7 |
Total Backlog |
5.0 |
24.5 |
29.5 |